AR
Log Date: December 21, 2011
Marking Period 2
Green Pier
12/21/11:
Work Started:
- research on materials
- research on 16 on center
- research on truss systems
Work Completed:
- window schedule
- emailed mentors about 16 on center
Reminders:
- finish door schedule
Dec 21, 2011
Dec 19, 2011
Dec 16, 2011
Log 10
AR
Log Date: December 16, 2011
Marking Period 2
Green Pier
12/16/11:
Work Completed:
- edited dimensions on CAD drawing
Work Started:
- additional research on materials for building purposes
Reminders:
- call mentor
Dec 13, 2011
Log 9
AR
Log Date: December 13, 2011
Marking Period 2
Green Pier
12/13/11:
Work Started:
- research on sun-path diagram
-materials list
Work Completed:
-
Reminders:
- talk to Environmental Science teacher for assistance with sun-path diagram
Log Date: December 13, 2011
Marking Period 2
Green Pier
12/13/11:
Work Started:
- research on sun-path diagram
-materials list
Work Completed:
-
Reminders:
- talk to Environmental Science teacher for assistance with sun-path diagram
Dec 9, 2011
Log 8
AR
Log Date: December 9, 2011
Marking Period 2
Green Pier
12/9/11:
Work Completed:
- attempt to attach materials to CAD drawing
Work Started:
- new CAD drawing
Reminders:
- check if mentor contacts over weekend
Log Date: December 9, 2011
Marking Period 2
Green Pier
12/9/11:
Work Completed:
- attempt to attach materials to CAD drawing
Work Started:
- new CAD drawing
Reminders:
- check if mentor contacts over weekend
Dec 6, 2011
Log 7
AR
Log Date: December 6, 2011
Marking Period 2
Green Pier
12/6/11:
Work Started:
- research on floor panels for heating
- research on lighting for inside
Work Completed:
-
Reminders:
- update mentor logs
Log Date: December 6, 2011
Marking Period 2
Green Pier
12/6/11:
Work Started:
- research on floor panels for heating
- research on lighting for inside
Work Completed:
-
Reminders:
- update mentor logs
Dec 2, 2011
Log 6
AR
Log Date: December 2, 2011
Marking Period 2
Green Pier
12/2/11:
Work Started:
- press release
- finishing touches to CAD drawing
Work Completed:
- press release
Reminders:
- call mentor
Log Date: December 2, 2011
Marking Period 2
Green Pier
12/2/11:
Work Started:
- press release
- finishing touches to CAD drawing
Work Completed:
- press release
Reminders:
- call mentor
Dec 1, 2011